2012 Muirfield Village Capital Improvement Projects
Water Line Replacement Project | Sewer Lining | AEP Cable
Improving and preserving the infrastructure of our resident neighborhoods is an investment in our City that adds value and high quality city services for our residents. The first phase of Muirfield Village was built 40 years ago. While these neighborhoods have maintained their beauty and real estate desirability – the infrastructure (sewer pipes, waterlines and underground utilities) are in need of repair and restoration.
In 2012, the City of Dublin will begin three Capital Improvement Projects, approved by Dublin City Council, designed to improve the infrastructure and services to sections of Muirfield Village.
While these improvements are needed and will extend the life of waterlines, sewer lines and underground electric cable – we understand there may be some inconveniences to residents during the construction. We want to provide you updated information, maps and contact information to direct questions and concerns.
Water Line Replacement Project
Muirfield Village Waterline Replacement Project Public Meeting
Residents of Muirfield Village are encouraged to attend a Public information meeting regarding the upcoming Muirfield Village waterline replacement project. Construction will begin in July 2012.
Presentation from the Tuesday, May 8, 2012 Public Meting

Leven Links Court

Milmichael Court and Dornoch Court
Muirfield Village Waterline Replacement Project
The City of Dublin is in the beginning stage of design for the upcoming Capital Improvement Project to replace and upgrade existing waterlines in the Muirfield Village areas of Levin Links Court West, Dornoch Court and Milmichael Court.
EMH&T has been hired to perform engineering services for this project. Their personnel will be on site beginning the week of January 30th to collect and mark survey field data of the utility, right-of-way, easement and property line locations. Construction will begin this summer.
The City will be hosting a public information meeting this spring/summer for residents directly affected by the water line project. Information will be sent to residents and posted online.
Download Map
- For additional information, or questions please contact C. Aaron Stanford, P.E. at 614.410.4676, or astanford@dublin.oh.us
2012 Sewer lining
Beginning the week of January 30, Reynolds Inliner, a contractor hired by the City of Dublin, will be in Muirfield Village installing Cured In Place Pipe (CIPP) in clay sanitary sewer pipe during the next few months. This will be the first phase of additional sewer lining projects in Muirfield Village. More information will be available as phases are scheduled.
CIPP will increase the life of the sanitary sewer pipe by 30 to 50 years, as well as re-establish the integrity of the sanitary sewer system by reducing clean water infiltration.
Some residents will need to reduce their water use for several hours during the lining process. City staff and/or Reynolds Inliner will personally notify these residents.
Download Map
Sewer Lining Update - April 5, 2012
The Muirfiled Village sewer lining Phase I, which began on January 30 in the area near Kilbannan Court, has been completed. Sewer lining is an important infrastructure investment in our community. The next phase of sewer lining in Muirfield, north of Glick Road, will begin in June after the Memorial Tournament. More information and maps on Phase 2 will be available this spring.
Emerald Parkway Bridge Construction
On Friday, April 6, from 8 a.m. - 4 p.m., there will be construction on the small portion of Emerald Parkway bridge over US 33. The road will be open, but motorists may expect some traffic delays.
Sewer Lining Update - February 27, 2012
The Muirfield Village sewer lining project continues to progress on schedule. To date, 4,879.5 linear feet of lining has been installed with more than 50 percent of the project completed.
Sewer Lining Update - February 10, 2012
The Muirfield Village sewer lining project began on Monday January 30 in the area near Kilbannan Court (see map below). During the past two weeks, Reynolds Inliner has installed 2,440 liner feet of the 9,339 foot project. To date, they have completed 26 percent of the project. The project is progressing on schedule with an anticipated completion date of March 15, 2012.

Download Map | Download Fact Sheet
-
For questions or concerns, please contact Bill Grubaugh at 614.410.4758 or bgrubaugh@dublin.oh.us
-
General information and answers to frequently asked questions can be obtained at: www.nationalliner.com
AEP Underground Electric Cable Replacement
AEP Update - April 24, 2012
Sections of Muirfield Village including Dunsinane Drive and Muirfield Court will experience a brief power outage on Wednesday, April 25, as AEP continues underground cable restoration and replacement work in the area. It is anticipated the outage will be one hour or less with a start time of 9:00 am. For questions or concerns, contact AEP's customer service center at 800.277.2177.
AEP Update - April 20, 2012
Section I was completed earlier this week and placed in service. Presently all the conduit has been bored in on Muirfield Court (shown in " dark blue" on the map) and is ready for the new conductor to be installed. The areas shown in "red" are presently under construction with target completion date prior to the Memorial Tournament.
Download Map
AEP Update - April 10, 2012
AEP has canceled the equipment switch over scheduled for this week. It has been rescheduled for Monday, April 16 starting at 9 a.m. Tuesday, April 17 will be the inclement weather back-up date. We will continue to post updates and information received by AEP.
AEP Update - April 6, 2012
AEP has been working on replacing underground cable lines in sections of Muirfield. The first phase of the work will be completed by the end of this week. On April 12 or 13 - AEP will be switching over to the new equipment in the area between Kinross and Muirfield Drive. Some residents in the area (see streets below)Â may experience an outage for a few minutes while others could be without electricity for 2-3 hours. AEP will notify us when they plan on switching the equipment. We hope to give residents enough notice so they can adjust daily activities.
Below is the list of the streets that are served by the facilities AEP will be switching either next Wednesday or Thursday.
Glenfinnan Ct
Gairloch Ct
Saint Fillans Ct W
Saint Fillans Ct E
Moray Ct
Levin Links Ct
Kinross Ct
Update letter from AEP on February 3, 2012
AEP began replacing underground electric cable lines in sections of Muirfield the week of January 23. The project is anticipated to be completed by early May. AEP will provide updates to residents and to the City on progress and work areas.

Download Map | Download Project Schedule
- For questions or concerns, contact AEP’s customer service center at 800.277.2177.